Dindoshi Court Refuses to Stop Borivali Society From Appointing New Developer

Source: Free Press JournalView source

A Dindoshi City Civil Court has refused a developer's plea to restrain Vrindawan (Borivali) CHS from signing with a new developer after it terminated a 2019 MOU, holding that the members' interest in long-delayed redevelopment outweighs the developer's claim.

The City Civil Court at Dindoshi, Mumbai, has refused to stop Vrindawan (Borivali) Co-operative Housing Society Ltd. in Borivali (East) from going ahead with a new developer for its redevelopment. City Civil Judge Supriya Nikam rejected an interim injunction sought by Magnus Construction Company, whose agreement with the 64-member society had been terminated. The ruling was reported on 7 November 2026.

Background of the dispute

The society and the developer signed a memorandum of understanding (MOU) for redevelopment in 2019. The society terminated the MOU in 2022, and the developer filed a civil suit in August 2023 challenging the termination. It said it had done substantial work, including helping the society obtain deemed conveyance at its own cost, and that the termination was illegal and contrary to the MOU. Pending the suit, it asked the court to bar the society from entering any redevelopment agreement or creating third-party rights in the property.

The society argued that no development agreement had ever been executed or registered, so there was no concluded contract that a court could enforce through specific performance (an order compelling a party to carry out a contract). It said the developer had sought changes to fundamental terms, including area entitlement, that its joint partner had withdrawn, and that timelines had been breached. The society said it terminated the MOU under a contractual clause and has since appointed another developer by a general body resolution.

What the court decided

The court held that the developer had not made out a prima facie (first-look) case for specific performance or for restraining the society, noting that the general body had already appointed another developer. It found that the balance of convenience lay with the society, since an injunction would cause greater hardship to members awaiting new homes, rent and other benefits after years of delay. The main suit remains pending, and the developer's lawyer said it would pursue its remedy there.

What this means for housing societies

  • An MOU alone may not bind a society the way a registered development agreement does; courts look closely at whether a concluded contract exists before blocking a society.
  • Termination of a developer should follow the termination clause in the MOU or agreement and be backed by a properly noticed general body resolution, as the society relied on here.
  • Courts weigh the hardship to members from delayed redevelopment when deciding whether to grant a stay, but a terminated developer can still pursue damages or other claims in the main suit.
  • Committees should keep records of timeline breaches, changes in terms sought by the developer, and any work done by the developer at its own cost, as these become central if the matter reaches court.

This was an interim order; the developer's suit challenging the termination has not been finally decided. Case numbers and the full text of the order were not available in the published report. Societies considering ending a redevelopment arrangement should review the exact termination terms in their documents before acting.

For informational purposes

This news summary is based on publicly available information and is intended for general awareness only. It does not constitute legal advice. For guidance specific to your society, consult a qualified legal advisor or housing society consultant familiar with your situation.