EV Charger in Your Housing Society: Can the Committee Say No?

13 November 2026 7 min readBy Puranik & Associates

Electric cars and scooters are now a common sight in Thane, Mumbai and Navi Mumbai society parking lots, and the requests that follow are just as common: “Can I install a charger at my parking slot?” Many managing committees are unsure. Some approve informally and worry later about fire safety and electricity bills. Others refuse outright, which leads to complaints and disputes. With the State’s EV Policy pushing charging infrastructure and the Bombay High Court having asked the authorities to settle clear rules for housing societies, this is a question every committee should have a written answer to.

The court and policy details below are based on published reports, not the full text of the orders or Government Resolutions. Check the latest Cooperation Department circulars or take advice before relying on any specific condition.

What the Bombay High Court said

In Amit Dholakia v. State of Maharashtra (Writ Petition No. 1580 of 2024), a resident of a Mumbai cooperative housing society approached the High Court after his society refused permission to install a charger in his garage. As reported, he asked the Court to direct the Registrar of Cooperative Societies to amend the Model Bye-Laws using the Registrar’s powers under the Maharashtra Co-operative Societies Act, 1960.

The State told the Court that the Additional Registrar (Housing) had already prepared draft conditions in July 2022 for approving EV chargers in housing societies. According to the reported affidavit, these drafts contemplated that an NOC should be granted where technical requirements are met, that installations follow Central Electricity Authority safety standards, and that adequate sanctioned load is available.

The Bench disposed of the petition with directions that the State finalise these conditions on a priority basis, that the Registrar circulate them to housing societies across Maharashtra, and that the Registrar consider issuing directions under Section 79A of the MCS Act to bring bye-laws in line. The State had also pointed out that a member aggrieved by a society’s decision can raise a dispute under Section 91 of the Act.

Where the State EV Policy fits in

Maharashtra’s EV Policy 2025 (Government Resolution dated 23 May 2025) places heavy emphasis on charging infrastructure. As summarised in published reports, it expects new residential buildings to be EV-ready and, for existing housing societies, allows shared charging spaces subject to approval by at least 50% of members, with the society responsible for safety compliance. Building-level requirements are to be brought in through planning and development control rules, so the exact obligations for your building depend on your municipal corporation.

The practical takeaway is that there are two different situations, and committees should not mix them up:

PointPrivate charger at a member’s own slotShared charging for the whole society
Who decidesManaging committee on a member’s applicationGeneral body resolution
Who paysThe member: charger, cabling, meter and electricitySociety or an operator, recovered through usage charges
Power sourceMember’s own meter or a separate sub-meterSeparate connection or common meter with metered billing
Key risksOverloading common wiring, unmetered use of common powerContract terms, allotment of slots, fire safety in basements

A fair approval process for committees

A society cannot be careless about safety, but blanket refusals are increasingly hard to defend and invite Section 91 disputes and complaints to the Registrar. A written, uniform process protects both the committee and the member:

  1. Written application from the member stating the parking slot (allotted or owned), charger make and rating, and proposed cable route.
  2. Electrical feasibility report from a licensed electrical contractor confirming the load, earthing, protection devices and route. Ask for the DISCOM’s load sanction where enhancement is needed.
  3. Metering arrangement so that no common electricity is used, either from the member’s own meter or through a separate meter or sub-meter.
  4. Undertaking and indemnity covering installation and maintenance costs, damage to common property, and removal on sale or change of slot.
  5. Committee decision within a fixed time, recorded in the minutes with reasons, and conveyed in writing. If conditions are imposed, list them clearly.
  6. Post-installation check by the society’s electrician, and inclusion of the charger in the society’s fire-safety and insurance records.

Never allow chargers to be plugged into common-area sockets or lighting circuits, and never permit charging cables to run loose across driveways. Unmetered charging from common power is effectively a subsidy paid by every other member and is a common trigger for disputes.

Member rights and practical tips

  • Apply in writing and keep proof. A WhatsApp request is easy to ignore. A dated letter with a technical report is not.
  • Ask for reasons. If the committee refuses, request the minutes recording the decision. Members have a right to inspect society records, as explained in our article on inspecting society records.
  • Know your parking position. Whether your slot is allotted by the society, a stilt or basement space, or covered by your agreement affects what you can install. See parking and basement rights.
  • Escalate in order. Committee first, then the general body, then a complaint to the Deputy Registrar or a dispute under Section 91 if the refusal is unreasonable.
  • Committees: adopt a policy at the next general body meeting. A one-page EV charging policy with standard forms ends case-by-case arguments and keeps decisions consistent.

This article is general information for committee members and flat owners and is not legal or electrical engineering advice. Court and policy details are drawn from published reports and should be checked against the original documents and any later Cooperation Department circular.